张良, 赖伟强, 李浩辉. 10 kV杆塔基础在复杂沙质土层的施工技术研究[J]. 农村电气化, 2024, (1): 18-20. DOI: 10.13882/j.cnki.ncdqh.2024.01.005
引用本文: 张良, 赖伟强, 李浩辉. 10 kV杆塔基础在复杂沙质土层的施工技术研究[J]. 农村电气化, 2024, (1): 18-20. DOI: 10.13882/j.cnki.ncdqh.2024.01.005
ZHANG Liang, LAI Weiqiang, LI Haohui. Research on Construction Technology of 10 kV Tower Foundation in Complex Sandy Soil Layer[J]. RURAL ELECTRIFICATION, 2024, (1): 18-20. DOI: 10.13882/j.cnki.ncdqh.2024.01.005
Citation: ZHANG Liang, LAI Weiqiang, LI Haohui. Research on Construction Technology of 10 kV Tower Foundation in Complex Sandy Soil Layer[J]. RURAL ELECTRIFICATION, 2024, (1): 18-20. DOI: 10.13882/j.cnki.ncdqh.2024.01.005

10 kV杆塔基础在复杂沙质土层的施工技术研究

Research on Construction Technology of 10 kV Tower Foundation in Complex Sandy Soil Layer

  • 摘要: 随着10 kV配电网网架地不断向农村地区发展,农村配电网升级改造也迎来更高的可靠性和安全性,文章以某110 kV变电站10 kV某线路改造工程为例,重点阐述10 kV配网杆塔基础施工,遇到复杂的沙质地质且无法变更杆塔位置时,所进行的施工技术优化改进。

     

    Abstract: With the continuous development of the 10 kV distribution network in rural areas, the upgrading and renovation of rural distribution networks have also ushered in higher reliability and safety. This article takes the 10 kV tower line renovation project of the 110 kV Dongping Station in Sihui, Zhaoqing as an example, focusing on the construction of the 10 kV distribution network tower foundation. When encountering complex sandy geology and unable to change the tower position, the construction technology optimization and improvement are carried out.

     

/