缩短500kV变电站主变消防改造时间
Time Curtailment of Fire-Fighting Renovation in 500 kV Substation
-
摘要: 根据华东电网变压器消防改造停电时间要求,500 kV变压器须在最大有效工作时长48 h内完成消防改造工作。目前,第一批消防改造的500 kV主变消防改造所需时间约为50.17 h,不满足主变消防改造计划时间要求。QC小组通过寻找要因并制定对策,改善问题症结,500 kV主变消防改造时间控制在39 h以内。Abstract: According to scheduled outages of East China Power Grid, The task of 500 kV transformer fire-fighting rehabilitation needs to be finished within 48 hours. Currently, however, 50.17 hours was consumed in the first plan to perform and finish the task of fire-fighting renovation, and the time requirement was not satisfied.The key of problem and solutions was searched by QC group, then, a goal that the renovation of 500 kV Substation was limited into 39 hours.